The Bond Corridor Project
The Public Lighting Authority of Detroit (PLA) is upgrading streetlighting across 33 of Detroit's major corridors through a $23.6 million bond-funded program. Crews are replacing aging wood poles and outdated fixtures with modern LED streetlights, new streetscape poles, and mast arms — improving visibility, safety, and the look of the City's busiest roads.
The program covers over 117 miles of corridors spanning all seven Council Districts, broken down by segments. Each segment goes through a full engineering review before construction begins to ensure the new lighting meets national standards.
Progress
Work is underway and progressing steadily, with over 102 segment miles already complete and additional segments in active construction. Residents can expect to see continued improvement along Detroit's corridors through the remainder of the program.
Engineering review
Every segment is reviewed before construction to meet national lighting standards.
Pole & fixture replacement
Aging wood poles and outdated fixtures come out.
Modern LED install
New LED streetlights, streetscape poles, and mast arms go in.
Residential Mid-block Lighting
Mayor Mary Sheffield and the Public Lighting Authority are investing $10 million to bring mid-block lighting to thousands of residential streets across Detroit.
Why mid-block lighting
For years, Detroit residents have raised concerns about dark stretches on their blocks. When the city rebuilt its street lighting system in 2014–2015, the upgrades restored lighting across main corridors and intersections to meet national illumination standards. But many residential blocks were left without adequate mid-block coverage.
Mayor Sheffield has championed this issue since her time as City Council President. Now the PLA will install at least 3,000 new mid-block lights on residential streets, improving neighborhood safety and quality of life across all seven council districts. The initiative focuses on areas where gaps in coverage have left portions of residential streets without adequate lighting.
Timeline
- April 2026Community input meetings across all seven council districts
- June 2026Final plan presented for PLA Board and Detroit City Council approval
- July 2026Installation of new mid-block lights begins
- November 2026Goal for completing the initial phase of installation
Community input shaped the plan
Before finalizing the lighting plan, the City of Detroit and the PLA hosted community input meetings in every council district. Residents reviewed initial findings on where mid-block lighting gaps exist, shared where additional lighting is most needed, and helped guide the final placement of new lights.
| District | Date | Location |
|---|---|---|
| District 1 | April 13 | Crowell Community Center (16630 Lahser Rd) |
| District 2 | April 15 | Adams Butzel Complex (10500 Lyndon St) |
| District 3 | April 20 | Farwell Rec Center (2711 Outer Dr E) |
| District 4 | April 22 | A.B. Ford Park (100 Lenox St) |
| District 5 | April 27 | Coleman A. Young Community Center (2751 Robert Bradby Dr) |
| District 6 | April 29 | Clemente Center (2631 Bagley St) |
| District 7 | April 30 | Carpenters & Millwrights Skilled Training Center (11687 American St) |
What comes next
This initiative is the first phase of a broader effort to address additional lighting needs across Detroit. Future phases may include alley lighting and decorative lighting improvements in some of the city’s historic districts.
Questions? Call the Public Lighting Authority at (313) 324-8290 or email info@pladetroit.org. To share where more lighting is needed, use the streetlight feedback survey.
More from the PLA
PLANT pre-apprenticeship
Training Detroit residents for careers in the skilled trades. See the highlights →
Street lighting modifications
Planning a project that needs streetlights relocated, temporarily removed, or upgraded at your own expense? Submit a Plan of Work request to PLA. Go to Development →